Agenda item

Ernst and Young, the Council’s External Auditors will present the report.  The Committee are invited to note the content of the Audit Results Report produced by the Council’s External Auditors, Ernst Young.

 

Minutes:

Click here to view a recording of this item on You Tube

 

The Chair explained that getting to this point to approve the Statement of Accounts had been difficult for all involved and congratulated Borough Council officers and staff at Ernst and Young for their arduous attention to the matter which would be the ongoing position for further years.

 

Prior to presenting the Annual Audit Results Report, M Hodgson, Ernst and Young explained that he would draw attention the Committee’s attention to the key areas, messages, and observations.  Members were informed that it had been a difficult audit over a period of time, which had presented major issues as set out below:

 

·         Delay in the preparation of the financial statements

·         Valuation of plant and equipment.

·         King’s Lynn Innovation Centre:  the impact on accounts, financial statements, and value for money.

·         Impact of Covid and the Borough Council’s response to the national pandemic had reduced the capacity to deal with the audit and queries raised.

 

M Hodgson, presented the Audit Results Report for the year ended 31 March 2019 and External ISA 260 Report and highlighted the following key areas:

 

·         Changes in materiality – overall materiality assessment updated to £1.733m

·         Audit risks/findings for discussion.

·         Fraud or error – a good outcome no matters were identified to report good news story.

·         King’s Lynn Innovation Centre accounting treatment for Norfolk and Waveney Enterprise Services Loan - audit adjustment of £953,000k which had been revised in the Borough Council’s Financial Statement.

·         Methodology and assumptions used in the valuation of the King’s Lynn Innovation Centre building.

·         Valuation of Property, Plant and Equipment  - total adjustment of £20m required.

·         Going concern disclosure Note 38, page 100 in the Council’s Statement of Accounts.

·         New accounting standards IFRS 9 and IFRS 15.

·         Finance Team capacity.

·         Summary of adjusted differences.

·         Letter of Representation.

·         Value for Money – section 5 – King’s Lynn Innovation Centre/NWES loan.

·         Impact of Covid.

 

M Hodgson outlined the recommendations which the Borough Council should take seriously and advised that at the current time Ernst and Young did not need to use its statutory powers.  It was noted that the External Auditor’s Opinion would be finalised by 29 January 2021.

 

In response to question from Councillor Bambridge regarding a time limit being implemented on the value for money risks recommendation, Ernst and Young concurred that a time limit should be attached and implemented as soon as practicably possible and recognised that some of these would be set out as part of the action plan attached to the Internal Audit report.

 

Councillor Collingham commented that she had been a Member of the Audit Committee Cross Party Working Group set up to examine lessons learned report for the King’s Lynn Innovation Centre and had been concerned of the loss of the Chief Financial Officer and asked if the departure of the postholder had impacted on the relationship of the Borough Council and NWES.  In conclusion, Councillor Collingham asked if it was normal practice to risk assess the loss of a key person and what checks and balances could be put in place if this occurred in the future.

 

In response, Ernst and Young commented that this had occurred to a number of clients where the capacity within finance teams had diminished over the years.  It was explained that the departure of the Council’s Group Accountant had left the authority  exposed with regard to the financial accounting and relationships.  However, the Assistant Director, Resources and Section 151 Officer was in the process of addressing the issues on behalf of the council.

 

The Chair added that the impact of the loss of key staff was an entry in the council’s Risk Register and explained that it was within the Committee’s remit to revisit this entry. It was noted that the Audit Committee received regular updates on the risk register and had previously made changes to the information presented.

 

In response to a question from Councillor Ryves on the adjustment required for the Valuation of property, plant and equipment  - total adjustment of £20m required, Ernst and Young explained that the incorrect methodology had been used in the valuations undertaken by the Internal Valuation Team.  Ernst Young advised that the issue had now been recognised and was being addressed.

 

Following a further question from Councillor Ryves regarding the transparency of the additional audit fees, Ernst and Young explained that the total of additional fees incurred for the extra work required had not yet been concluded.

 

Ernst and Young responded to questions with regard to the King’s Lynn Innovation Centre loan to NWES and the repayment plan.

 

Ernst and Young also responded to questions on the Norfolk Pension Fund and the borough council’s contribution.

 

Under Standing Order 34, Councillor Rust addressed the Committee in relation to the Internal Audit Report and 35 recommendations on the King’s Lynn Innovation Centre.

 

Under Standing 0rder 34, Councillor Morley addressed the Committee in relation to the General Fund and asset valuation.

 

The Chair explained that the Audit Committee would continue to meet as scheduled to consider essential items only.

 

The Chair reminded Members of the Joint Panels Meeting on 26 January 2021 when the Assistant Director, Resources/Section 151 Officer would give a presentation on the council’s budget plans.

 

M Hodgson and the Assistant Director, Resources and Section 151 Officer responded to questions from Councillor Spikings on the impact on the council’s insurance policies if assets were undervalued.

 

The Leader thanked Ernst and Young for the work undertaken on the council’s audit. 

 

The Chair explained that the Audit Committee was the only council body that the accounts were presented to and asked the Democratic Services Officer to check if that was correct.

 

RESOLVED:  The Committee noted the content of the Audit Results Report produced by the Council’s External Auditors, Ernst and Young.

 